Inspection Performed By: TRISHNA PRADHAN
Inspection Date: 2023-03-01
Completion Date: 2023-04-12
Notes: • The repair work is on-going & is being installed per engineer’s design. Please see attached email from the engineer. However, the exterior / finish wythe is also being completed as CMU & I instructed the GC that the exterior wall has to be brick masonry; brick size has to match existing brick. I will email owner as well.
• The repair work being completed is in line with structural engineer’s report
- Exterior finish has to match the historic fabric of the rest of the building/. GC is aware of this- owner is being informed as well.
As of 3/1 bi-state was off the job-site because the owner did not agree to their Change order for installing brick outside.
Repair work is on-hold but shoring is in place & site is secure. Owner has not submitted new timeline for work to commence.
Inspection Status: Incomplete